CONSTRUCTION PERMIT INSPECTION REQUEST
Per the State of New Jersey, N.J.A.C. 5:23-2.18 (c), ALL inspection
requests must now be made in writing.
Inspections shall be performed within three business days, or other such
time within 30 days, as agreed upon by the enforcing agency and the owner,
agent, or other responsible person in charge of work, of the time for which it
is requested. The enforcing agency shall
notify the owner, agent, or other responsible person in charge of work when the
inspection will be performed within 24 hours of official receipt of the notice.
1. All of the required information below must be
provided including the permit number, worksite address, the requestor’s name
and phone number.
2. Select all applicable Subcodes and indicate the type
of inspection you are requesting.
3. Indicate the inspection date you are requesting.
4. Note: The
inspection request must be confirmed by the Department Staff before it is added
to the schedule. Due to scheduling, it
may not be the date requested.